Black box theater first, then amphitheater – maybe

Following the recommendation of the administration, the Redevelopment Agency is moving forward on a black box theater while prioritizing parking over an amphitheater in the short term.

The Redevelopment Agency on Wednesday awarded a $5.825-million construction bid to Gingerelli Bros, Inc. The Toms River-based firm was the lowest among 16 bidders to renovate the former Bell Building on Hamilton Street into a 220-seat black box theater. The award includes a base bid of $5.757 million and alternate bid of $27,112 for a folding partition and $41,200 for a metal roof instead of asphalt shingles.

City Administrator and Redevelopment Director Peter Pelissier said the city has approved $12 million for both a black box theater and amphitheater and even with the elimination of one project, more money would have to be raised for a parking facility. The 1,300-seat amphitheater planned at the former Hamilton Laundry site cost more than the original estimate and he recommended to commissioners first building the black box theater and creating parking at the amphitheater site for the time being given the economy and city’s looming debt, such as the school system’s $34-million renovation projects. Officials estimated some $2.73 million already has been spent on architect and engineering fees and other site preparation.

There were six bidders for the amphitheater, the lowest from Berto Construction at $4.734 million ($4.2 million base bid plus $487,000 in alternate bids). Other bidders included W.D. Snyder Co., $6.15 million, and CGT Construction, $6.21 million. The amphitheater project had to be re-bid after an issue arose with the original bids, challenged by one of the bidding companies, last fall.

Former Mayor James Kennedy, now executive director of the Rahway Arts District, said the merits of building the black box theater first are basic. A black box theater would have a year-round revenue stream while removing a building that’s been blighted for over a decade. If the amphitheater was pursued first but the project ran out of money, the blighted Bell Building would remain. In addition, the amphitheater site could provide needed parking for the black box theater.

Pelissier said parking is very stressed from Grand Avenue to the arts center so for the moment, parking is more important than an amphitheater. He said it will cost $300,000 to cap the amphitheater site anyway and another $150,000 would bring a parking lot that the Parking Authority could use as a temporary revenue stream.

As currently designed, the Hamilton Street arts projects would have 48 parking spaces but creating parking at the amphitheater site would add 86. The agency was presented with an option to add two lots, the first of which would gain 16 spaces behind four homes currently stand on Hamilton Street for a total of 134 spaces (design at right). The second lot would add 138 spaces, losing 16 to reconfiguring spaces behind the homes but adding about 36 in the area of the homes, for a total 170 spaces (design above). The first lot included parking behind the homes. (Click the images to enlarge).

The bid that was awarded only includes parking behind the black box theater but not the additional parking at the amphitheater site, Pelissier said. That would have to be designed and bid, which the administration recommended pursuing separate bids for as early as next month.

Mayor Rick Proctor called it the “most common sense” solution at the moment because of the year-round revenue available from a blackbox theater as opposed to the seven to eight months from an amphitheater. “It’s the best to prioritize use of the money we have available,” he said.

A cautionary tale for arts-based redevelopment?

An effort started in the 1980s and ’90s by downtown merchants to encourage people to shop there, centered around a renovated 1930s-era performing arts center. Loft housing for artists created with the help of tax dollars and a new zoning category to allow live-work rental properties. Sound familiar? No, it’s not Rahway.

Continue reading A cautionary tale for arts-based redevelopment?

Amphitheater to be re-bid

A judge ruled this week that construction bids for the Hamilton Street amphitheater must be re-bid.

Redevelopment Director and City Administrator Peter Pelissier said there was some ambiguity about some portions of the lowest bid, which was rejected, and so the judge felt it should be re-bid.

Opening of new bids is scheduled for Dec. 15 and is scheduled to be awarded at the Dec. 22 Redevelopment Agency meeting.
Groundbreaking could occur as early as mid-January, according to City Engineer James Housten.

The Redevelopment Agency awarded a $4.95-million construction bid last month to Rahway-based Berto Construction, however, Kenilworth-based W.D. Snyder Company had the lowest base bid at $4.65 million but it was rejected as a “deficient bid proposal” for a “material breach.”

The facility originally was anticipated to open in May and be ready for use in July, said Pelissier, adding that the timeline could still be feasible.

***

For those interested in a district-by-district breakdown of Tuesday’s election, here they are in a Google spreadsheet. Democrats carried about 60 percent of the vote in local races, with Rick Proctor carrying 16 of 24 districts for mayor against Pat Cassio, who carried the 3rd and 6th wards. Turnout was about 48 percent.

Mayoral candidate: Rick Proctor, Democrat

Note: The two major-party candidates for mayor were invited to submit a blog post (no more than 750 words) about their redevelopment platforms. Entries were edited only for spelling and style. Also on the ballot in the Nov. 2 election are three At-large City Council seats. Today’s post comes from Democrat Rick Proctor. Republican Pat Cassio appeared Monday morning.

Continue reading Mayoral candidate: Rick Proctor, Democrat

Piano Conservatory opens

Conservatory: Piano, Hi Fi and Modern Home opened its doors Friday night for a “sneak preview” at its new home next to the Union County Performing Arts Center.

The conservatory will feature educational programs, a piano showroom, state-of-the-art audio equipment, vintage jazz and classical vinyl recordings, and recording studios.

Friday’s event included performances on pianos from the Klavierhaus collection as well as demonstrations of the equipment. “Our new multi-faceted space has been created for the pursuit of fine living through musical education and the leisure of experiencing music in the home,” said Peabody Award-winning and Latin Grammy-nominated radio and record producer Jim Luce of Piano Culture.

Renovations to the single-story building at the corner of Irving and Coach streets, which once housed the Rahway Alternative Education Center, could run upward of $20,000 once the HVAC system is replaced, according to Mayor James Kennedy, who also serves as a board member of UCPAC and the unpaid executive director of the Rahway Arts District. The arts center owns the building and will cover the cost of renovations, which included a new roof, he said, while leasing it to Luce and his partners.

‘Shipping containers’ explored for artist housing

Seven artists picked to live in shipping containers behind the Arts Guild? It could make for an interesting season of MTV’s The Real World, but it’s also an idea being explored as one avenue to bring affordable housing to the city for artists.

In a presentation before the Redevelopment Agency last week, representatives of Global Building Modules (GBM) Design Consortium outlined several different preliminary schemes that would site seven modules in the area behind the Arts Guild at Irving Street and Seminary Avenue. The units would be laid out in a way to include shared green space and concert lawn or some type of performance space with a capacity of 50 to 70 people.

Based on shipping containers, the modules are manufactured overseas and buildings can be constructed in a fraction of the time and cost of traditional construction, according to GBM. Transportation costs also are considerably lower since there is no need for special escorts or permits.

Modules retain only the dimensions of shipping containers (roughly 40 x 8, or about 1,280 square feet) and are designed with the aim of zero net energy use, reducing the carbon footprint that comes with traditional construction. The exterior envelope of the structure is wrapped with insulation, windows can be placed anywhere and facade materials can vary. Modules can be organized in different ways, with varying room dimensions. They also are reusable and can be unbolted and reconfigured, or added to another building.

GBM said it has an ongoing relationship with New York University for high-rise housing in Greenwich Village, where modules also can minimize neighborhood impact during construction. As many as a dozen modules can be installed by crane within two days and facades could be seen within three months. They also pointed to projects at 11 Great Jones St. and 135 Crosby St. in Manhattan.

David Wallace of GBM reminded the Redevelopment Agency that the presentation was strictly provisional, “putting ideas out there that are works in progress; they’re not fixed ideas on our part.” Future discussions will focus on programs, the connection to the Arts Guild, music versus art studio space, performance space configurations, LEED goals and energy performance, he said.

The environmental impact of green building has caught the attention of major foundations, according to Mayor James Kennedy, who has sought to include affordable housing for artists to sustain the arts as part the overall redevelopment plan for the city. “Four years ago you couldn’t find a developer who’d do this type of project,” he said, confident that the industry will blossom in the coming years.

Kennedy said the design phase is likely to take many months while the use of Zipcars also will be examined. About seven selected artists, perhaps three performing artists and four visual artists, would act as caretakers of the installation, he said. The Guild site is small enough to test ideas for larger projects, such as the former Elizabethtown Gas building, which could be home to 30 to 70 units of artist housing in the future, Kennedy said. The mayor often talks about retaining artists who come to inexpensive neighborhoods only to get priced out by gentrification.

City Administrator and Redevelopment Director Peter Pelissier said the proposal is still very preliminary and there will be further presentations regarding the economics and costs and how the city can address artist housing.

Amphitheater groundbreaking expected in fall

City Council last month authorized bid specifications for construction of the Hamilton Street amphitheater. The project is expected to break ground in September.

Continue reading Amphitheater groundbreaking expected in fall

Agency acquires another Hamilton Street home

The Redevelopment Agency earlier this month approved the purchase of another Hamilton Street home as part of projects within the Arts District.

Continue reading Agency acquires another Hamilton Street home